How to Build a Lubrication Route: Points, Lubricants and Intervals
A lubrication route turns scattered grease points into one walkable, repeatable task. Here is how to inventory points, set intervals and sequence the route.

The Friday grease gun problem
A planner inherits a plant where lubrication is "handled." Two senior mechanics know which grease fittings matter, which gearbox takes which oil, and which bearing gets a few pumps and no more. One of them retires. The other is out sick the week a conveyor drive seizes.
Nobody can say when that drive was last greased. There is no list. There is a grease gun with a taped-on label, a few handwritten notes in a toolbox, and a half-remembered rule that the "blue grease" goes on the fans. The failed bearing gets replaced, and the question comes up again: what else are we missing?
That is the situation a lubrication route is built to prevent. A route takes lube points that live in people's heads and puts them into one inventory, one sequence and one log. This guide walks through lubrication route planning from the first walk-down to the first logged round, so you can build a route your whole crew can run without asking the person who knew it all.
Why lubrication deserves its own route
Lubrication tasks are small, frequent and easy to skip. A technician rarely notices a missed grease point the day it is missed. The cost shows up later, as a bearing that runs hot or a seal that lets go.
Bearings are where this pays off. According to Machinery Lubrication (Noria), bearing failures account for 50%–65% of all electric motor failures, and poor lubrication practices account for most of those bearing troubles (Machinery Lubrication/Noria, 2018). Motors are only one asset class, but the pattern carries: lubrication is a planned, repeatable task, and failures here are often avoidable with discipline.
A route solves a different problem than a PM schedule does. A schedule says "grease the motor bearings every so often." A route says which fitting, which lubricant, how it is applied, in what order you walk to it, and where you record what you did. The schedule tells you something is due. The route tells a technician exactly how to do it.
Keeping lubrication on its own route also protects it from the rest of the PM load. When it is folded into a general PM work order, it is the first line item to get a quick checkmark. A dedicated route makes it visible and countable.
Step 1: Inventory every lube point
You cannot plan what you have not found. Start with a physical walk-down, not a spreadsheet.
Walk the plant with a clipboard or a tablet and a camera. At each asset, find every point that takes lubricant. For each one, capture:
- Point ID. A short unique code, such as the asset tag plus a letter (for example, the drive-end bearing on one motor and the non-drive-end bearing as separate points).
- Asset and location. Which machine, and where on it. "Drive-end bearing, left side" beats "motor bearing."
- Point type. Grease fitting, oil reservoir with sight glass, oil bath, chain or open gear, slide or way, or a sealed-for-life component that takes nothing.
- Access notes. Guard that must be removed, lockout needed, point only reachable when running, or an extended line that someone added.
- Current lubricant. Record what is in use today, even if you are not sure it is right. You will check it in step 2.
Take a photo of each point and attach it to the record. Photos settle arguments and help a new technician find a fitting that is hidden behind a guard.
Expect surprises. You will find fittings no one remembered, points with no fitting at all, and assets where two different greases are in use. Write all of it down. A grease point inventory with gaps in it is still better than the folklore it replaces.
Sealed-for-life components deserve a line too. Record them with "no lubrication required" so nobody wastes time wondering whether they were missed.
Step 2: Assign lubricants from the manual, not from habit
Once the points are listed, assign one lubricant to each. This is where plants get into trouble, because the lubricant in the gun today is often there by habit or by whatever was in the storeroom.
The authority is the equipment manufacturer's manual. It specifies the lubricant type and grade for each point, and it often specifies the application method and amount. We do not publish grades, quantities or intervals here, because they differ by manufacturer, model and duty. Copy them from the manual, and where the manual is missing, ask the manufacturer or your lubricant supplier.
For each point, record:
- The lubricant specification from the manual.
- The product you stock that meets it.
- The application method (grease gun, drip, bottle, auto-lubricator, bath).
- The quantity or fill level the manual gives.
Then look for ways to reduce the number of products on the floor. If five points specify greases that your supplier confirms are compatible and equivalent, you may be able to consolidate. Do that only with the supplier's confirmation, and keep the manual spec on the record. Mixing incompatible greases is a known way to turn a lubrication program into a failure source, so never consolidate on a guess.
Label every grease gun, can and funnel with the product name. Many plants use color coding so that the product on the container matches the product on the route sheet.
Step 3: Set intervals and choose the trigger
Each point needs an interval. Start from the manufacturer's recommendation and record where it came from. That source note matters later, when someone asks why a point is greased monthly instead of quarterly.
Intervals can be driven by:
- Calendar time. Every week, month or quarter. Simple, and the right default for most routes.
- Operating hours or other usage. Better for equipment that runs irregularly. If you track run hours, a usage-based trigger keeps the interval honest. Calendar-based route tools do not do this for you, so track the meter reading in your PM schedule and flag the route when it is reached.
- Condition. Oil analysis, temperature or sound checks can shorten or extend an interval. Treat these as adjustments you make deliberately, with a note on why.
Adjust for duty, but do it with a reason on the record. A motor in a hot, dusty, washdown or high-load environment may need a shorter interval than the manual's baseline conditions assume. Write the reason next to the number. The change should be something you can defend, not a feeling.
For reference on how intervals are reasoned about across equipment types, see the PM interval reference library guide. Treat any interval you find there as a typical starting point and verify it against your manufacturer's guidance.
Group points by interval where you can. A route that mixes weekly, monthly and quarterly points on a single walk needs a clear flag on which points are due this round. Many planners build separate weekly and monthly routes, then fold the quarterly points into the monthly walk in the right month.
Step 4: Lubrication route planning by walk order
Now sequence the points. This is the part that makes a route a route.
Order the walk by physical location, not by lubricant or by asset number. A technician should move through the plant in one pass, without doubling back. Draw the route on a floor plan or number the points in the order they will be reached.
A few rules that save time:
- Group by area first. One zone, one pass.
- Put restricted-access points together. If three points need a guard removed or a lockout, do them in one stop.
- Separate running and stopped work. Points that must be done only when equipment is down belong on a different route, or flagged to be scheduled with an outage.
- Keep the carry load realistic. If a route needs four different products, set up a cart or a labeled kit rather than a tool bag of unmarked guns.
- Cap the route length. A route that takes a full shift is a route that gets skipped. Split long routes by area, and assign each a realistic duration.
Link the route back to the asset-level PM checklists so the lubrication task is not duplicated. The electric motor PM checklist, gearbox preventive maintenance, centrifugal pump PM guide and conveyor preventive maintenance guides each cover how lubrication fits with the other tasks on that asset. If the route owns the greasing, the asset PM can simply say "see lube route."
Route walks are also a free inspection. A technician at a bearing is already looking at it. Add a few observation prompts to each stop, such as leaks, unusual noise, heat, loose guards and missing caps, and give the technician a place to flag a finding.
Step 5: Log what was done and review the route
A route without a log is a set of good intentions. The log is what turns the route into evidence, and it is what lets you improve the program.
For each round, record:
- The date and who walked the route.
- Each point marked done, skipped or not accessible, with a reason for any skip.
- Any condition found: leak, contamination, noise, heat, damaged fitting.
- Anything that was changed, such as a replaced fitting or a swapped product.
Then calculate your own completion rate the same way you would for PM compliance: completed lube tasks divided by scheduled lube tasks, times 100, over a rolling window. Say eight of ten scheduled points were done this round. That is 8 ÷ 10 × 100, or 80%. This is a worked example, not a benchmark. The point is that you can compute a number from your own log and watch it over time.
Good lubrication route planning includes a review on a set cycle. Look at what the log shows:
- Points skipped round after round. They may be unreachable, mislabeled or not worth a task.
- Findings that repeat on the same asset. That asset may need a PM change or a closer look.
- Products that have changed. Update the inventory so the next technician is not working from stale data.
- New equipment added to the floor. Every new asset should arrive with its lube points added to the route.
A route is never finished. It improves each time someone walks it and writes down what they found.
Putting the route in a template
You can run a lubrication route from a plain spreadsheet. The inventory is one table, the route sequence is a sort order, and the log is another table. The risk is that the list drifts, the due dates are calculated by hand and the log lives on a clipboard.
The Lubrication Route Planner & Log is built for this. You enter points, lubricants and intervals, and it shows which lube tasks are due and overdue by route. It is a spreadsheet template, so it works from the data you enter, and it is a starting point rather than a CMMS. You can browse it at the Lubrication Route Planner & Log and adapt the columns to your own plant.
Whatever tool you use, lubrication route planning comes down to the same work. Walk the plant, list every point, take lubricants and intervals from the manual, sequence the walk by location, and log every round. Do those five things and the knowledge stops living in one mechanic's head.
Ready to go beyond the guide?
Get more guides like this in your inbox
Related guides
Equipment PM GuidesInstrument Calibration Schedules for Small Plants: Intervals, Status and Records
Calibration slips when due dates live in a binder. This guide shows how to register instruments, set intervals and keep a certificate trail an auditor can follow.
Equipment PM GuidesIndustrial Boiler Preventive Maintenance Schedule and Checklist
Boiler failures are expensive and sometimes dangerous. Here's how to build a PM schedule around inspection intervals, water treatment, and safety-device tests.
Equipment PM GuidesOverhead Crane Preventive Maintenance Checklist and OSHA Inspection Requirements
Overhead cranes carry some of the highest criticality scores in a plant. Here's the inspection checklist and interval logic tied to OSHA 1910.179.